title: Sprint 2 design harness for API/MM-Cron and MWMC — who does what, prompt queues, and the week before (25–31 Oct) status: accepted direction (Atul, 24 Oct: Sonnet expedites API/MM-Cron and MWMC alongside the harness); queues live in docs/prompts/ author: Claude (chat, MMDEP-PM) date: 2026-10-24 related: TD-025, TD-032, TD-033 (technical-decisions register); plans/direct-agents-design-harness-horizons §B; roadmap v4


Sprint 2 design harness: API/MM-Cron and MWMC

Sprint 2 runs 1–14 Nov. This week (25–31 Oct) we run the design harness once by hand on both projects, so sprint 2 starts with designs, ready issues and agents that know their queue. Five workers, each in its lane:

Worker Role Lane / scope Where it writes
Claude (MMDEP-PM) Designs the queues (this document). Reviews high-risk LLDs (API write-route enforcement, NAV de-duplication on production). Keeps the decision register design, decisions MMDEP
API agent A (current ChatGPT project) Lane P: production and high-risk API work api.moneymarche.com, security, contracts, production data fixes GitLab api / mm-crons, branches into production only with Atul's approval
API agent B (older ChatGPT project, resumed; API-2) Lane S: staging, data load, MR clean-up, OpenAPI, MM-Cron logging and inventory, low-risk code stgapi, api-phase1-development, mm-crons staging GitLab api / mm-crons, lane:staging
MWMC agent (ChatGPT) Page types, test plans, SEO audit triage, section inventory with WPDev website and webapp tests GitLab sandbox / webapp, MMDEP relay
Sonnet (Claude Code) Builds the tools both projects need, in MMDEP, running on the laptop runner against staging and production read-only: NAV data-quality checker, contract tests, Lighthouse CI, crawler checks. No GitLab write is needed MMDEP tools/ and tests/, jobs register MMDEP (merge by risk)
Local code harness Low-risk issues with routing blocks: tests, docs, small fixes, in api lane S and MMDEP for:code, risk low GitLab api (B8 source), MMDEP

Atul: one PROCEED per agent per day at most; business questions only, through for-atul (TD-024).

The loop for each project (TD-025)

  1. The queue file docs/prompts/<lane>/S2/QUEUE.md lists numbered steps. Each step gives: owner, inputs, outputs (exact paths), a check, and the harness job that follows.
  2. On PROCEED, the agent takes the first step whose dependencies are done, delivers it, and records runs/<step>.md in its repo (or the MMDEP relay for GitLab agents without a repo path). Then it continues with the next step, until it is blocked or the queue is empty.
  3. After each step: CI checks it, and the post-step job (B40) or Sonnet's tools act on it. For example, an LLD with a work-items table becomes ready issues (mmdep design issues, B36), which the harness picks up.

Week of 25–31 Oct (design-harness rehearsal)

Day API agent A (lane P) API agent B (lane S) MWMC Sonnet Harness
Sat–Sun — Atul resumes it with the API-2 prompt reads the SEO audit (relayed by inbox-relay) PROCEED: unstarve the harness, B42 model roles, then S2 tools idle until issues are ready
Mon–Tue P1: write-route security LLD → enforcement plan with a work-items table S1: MR clean-up (23 api + 22 mm-crons → at most 5 each) M1: page-type classification of the URL inventory T1: NAV data-quality checker; T2: Lighthouse CI job runs ready issues from S1 and M1
Wed–Thu P2: NAV duplicates on production: root cause and de-dup design (high risk, Claude reviews) S2: staging data load plan, run step 1 M2: SEO audit → issues and crawler checks T3: contract tests for routes used by MWMC/PE/WPDev; T4: crawler dead-end/CTA/SEO checks issues from P1/M2 work items
Fri P3: /api/health on production; /category flags fix ready for release S3: fix staging index/nav 404 and nfos 500; OpenAPI draft M3: test plan per page type, with the section inventory from WPDev T5: sprint metrics in the sprint page —

Done by 31 Oct: - every S2 story has an LLD or an issue list; - at least 10 ready low-risk issues sit in the harness queue; - the four Sonnet tools are merged and run daily.

Sprint 2 stories (1–14 Nov) for these two projects

Story Owner Value (roadmap v4)
API write routes secured on staging, consumers on keys; production enforced with Atul's approval A (P), B (S) risk reduction (security)
NAV duplicates and gaps fixed, with a daily checker green for 7 days A (P) design, B (S) staging, Sonnet checker data quality, PE and website trust
Staging loaded from cleansed production data; stgapi routes match production B (S) unblocks staging tests
OpenAPI for catalogue and NAV routes; contract tests B (S), Sonnet MCRM, PE, WPDev integration
MM-Cron logging and direct-DB inventory; fund details for all AMCs (TER, size, inception) B (S) R1 fund pages
MWMC: page-type tests, Lighthouse budgets, SEO audit fixes tracked, dead-end/CTA checks daily MWMC, Sonnet R1: impressions and minutes
First fund factsheet page from the production API MWMC + A (P) R1

Measured on the sprint page: stories done, harness-merged PRs, first-pass CI rate, steps per PROCEED, Atul-minutes.